Q1 lead times mostly stable, says Sourcengine
  Sourcengine has published its Q1 lead time report.
  Volatile memory is at 11-17 weeks and going up and NV memory is at 13-19 weeks and is mostly going up or,if not,is stable.
  Storage is at 10-15 weeks and mostly going up.
  Discretes are at 20-47 weeks and stable
  Standard logic and linear are at 7-20 weeks and mostly stable
  Advanced analogue is at 23-41 weeks and mostly stable
  Embedded processors are 15-48 weeks and mostly stable
  Programmable logic is at 20-25 weeks and stable